CP
is meeting todays changing industry needs
Each
Power Control Center is designed, built, and tested
at CP to fit your specific needs and NEC/UBC standards.
Installed equipment often includes medium and/or low
voltage AC switchgear, DC switchgear, metal enclosed
Bus Duct, power transformers, rectifiers, metering,
battery systems, SCADA panels, UPS systems and relay
& control panels.
After
your PCC leaves the factory, CPs support can
continue with shipment on dedicated trailers. CP's
value-added services can include site testing, site
erection supervision, and start-up services; a total
design/build service for the most demanding sites.
The
growing demand for CPs Power Control Centers
has come as a result of the changing needs of several
industries.
--------------------------------------------------------------------------------
PCC Classification
As
defined by UBC and NEC standards, Power Control Centers
are considered as electrical equipment enclosures, designed
for short-term occupation by personnel for only maintenance
and monitoring purposes.
Specifically:
Efforts should be made at project initiation to educate
local zoning and inspection agency staff as to the legal
classification of PCCs to avoid disputed or misunderstandings
later. PCCs do not require building permits nor inspections
in most situations.
1. The need to control total installed costs of new
substation projects.
PCC solution: Over 30% savings due to economies in factory
vs. site construction and testing. PCCs take less
square footage than a standard block building, requiring
only a concrete pad or concrete pier for construction,
thereby eliminating multiple contractor liaisons and
reducing overall Project Management costs.
2. The need to quicken new substation projects due to
tight deadlines.
PCC
solution: Substation construction and installation are
separated. Projects are built faster in a factory. Each
finished PCC can be shipped to sites and energized within
days.
3. The need to improve appearances and safety of substations
in urban areas.
PCC
solution: Substation enclosures appear to be industrial
buildings, containing locked doors and sealed roofs,
walls, and floors. CP can offer you a 20-year written
warranty for roof and wall panels as well as a wide
variety of colors and surface textures.
4. The need for design flexibility in economically expanding
substations for later growth plans.
PCC
solution: Expansion areas can be included in PCC designs,
or walls can be designed for expansion to a larger PCC
configuration at a later date.
5. The need to know that the substation will pass testing
standards without costly field debugging.
PCC
solution: Stringent PCC testing can be done at CPs
factory while the PCC is being built. Any potential
problems are handled in-house, affordably. The same
test technicians that performed the factory testing
are available for field start-up testing and commissioning.
Standard PCC Features
·
125 MPH wind load for assembled PCC
·
Zinc plated exterior hardware
·
Weatherproof gasketing is EDPM adhesive backed
·
Interior lighting features 48", dual receptacle
fluorescent tube fixtures
·
Light switch and duplex receptacle (qty. 2 each)
·
Panic hardware single-point latch touch bar exit
device
·
Door closer hydraulic with hold open feature
·
Expandable ends
·
Baked, dry powder epoxy coating on all metal surfaces
except structural steel base
Standard
Door Features
·
Steel flush door typical
·
Paintable 16 gauge A60 galvanized steel
·
1 ¾ " thick construction
·
42" wide x 84" high
·
16 gauge A60 galvanized steel door jambs
·
Drip shields over all doors
·
Equipment rear doors are standard
Standard
Wall Features
·
36" High gloss, white interior wall panels
·
2.5" Thick wall construction
·
24 Gauge epoxy coated galvalume exterior wall and roof
panels
·
Heavy duty interior framework throughout for strength
and rigidity
·
Absolutely no exterior hardware except for doors
Standard Roof Features
· 24 Gauge epoxy coated gavalume roof panels
·
Slope = 0.5" per 12"
·
80 lb./sq. snow or roof load
·
Interior steel ceiling
Standard
Base Features
·
ASTM A36 structural steel
·
3/16" Thick steel floor plate (¼" is
optional)
·
250 lbs./sq. Foot floor loading
·
Cover plates for conduit/cable entry areas
·
Grounding pads
·
Lifting provisions from the base
Available
PCC Options
·
Undercoated structural base
·
Insulated structural base
·
Electrically insulated floor coating
·
Separate battery room
·
Windows in walls or doors
·
Additional duplex receptacles
·
Panic Hardware two-point latch touch bar exit
device
·
Panic Hardware three-point latch touch bar exit
device
·
Door options single, double, louvers, fire-rated,
window
·
Double-wide Equipment access doors
·
300 series stainless steel exterior hardware
·
Air conditioning/Heat Pump/Ventilating fans
·
Electric Heaters
·
Pressurization system
·
Louvered panels
·
Clean air stacks
·
Exterior lighting with Photo Cell
·
Door "crash" stops
·
Interior Partitions (walls/compartments/battery room)
CP
stands out against the competition
Power Control Center
Concrete Building/Butler Type Building
Major Electrical Equipment
Same as Block Building.
Same as Power Control Center.
Design and Engineering
Complete package design and engineering by Controlled
Power. We manufacture the metal clad switchgear, low
voltage switchgear, bus duct, relay and control panels.
One stop shopping for all your electrical needs.
Purchaser responsible for Engineering, Design, Purchasing,
and Expediting for all major equipment as well as coordination
with building design firm and site contractors.
Power Control Center is designed for ease of expansion.
Generally, building space is shared with mechanical,
instrument, and operating people. This means the Electrical
Group must fight for every square foot of floor space
with minimum space for spare units and future expansion.
Frequently, the civil group using the electrical budget
performs building design. This blank check can lead
to a cost far above budget.
Power Control Center offers one-stop shopping and unit
responsibility.
The old method requires multiple specifications and
several rounds of soliciting and analyzing proposals.
This results in split responsibilities, even if the
electrical equipment is from the same vendor.
Power Control Center is factory wired complete with
schematics, wiring diagrams and conduit layouts. Changes
can be made after functional checkout at factory in
a controlled environment.
Purchaser must prepare integrated schematic and interconnect
diagrams for various types of equipment. Any changes
must be made, by the contractor, subject to job site
environmental conditions and at premium field labor
rates.
Power Controlled Center is completely factory tested
as a unit under single responsibility of CP.
Contractor must make and check all interface connections
between various types of equipment in the field at very
expensive labor rates.
Building Construction
Power Control Center can have hinged access panels behind
equipment.
Block building must be 25 to 40% larger to permit access
to rear of equipment in accordance with NEC.
Power Control Center requires a minimum foundation (i.e.
curb type, pier type, or perimeter vault).
Block building requires full slab foundation with relatively
large stem walls and footers.
Power Control Center is easily adaptable to overhead
or underground conduit systems.
Block building with slab floor requires a detailed and
exact conduit system that is difficult to change once
the floor is poured.
Grounding system is designed into Power Control Center.
Grounding system must be planned and built into foundation.
Provisions for future expansion must be made with initial
installation.
Power Control Center involves a minimum number of crafts
working at fixed factory rates.
Building requires many union crafts, i.e. laborers,
carpenters, iron workers, cement finishers, bricklayers,
electricians, etc. Each trade generally requires a foreman
and helpers, all at high labor rates.
Power Control Center often includes bus duct for transformer
secondary that is checked for ease of assembly before
shipment.
Purchaser must coordinate bus duct and other equipment
and hope that everything matches electrically and mechanically.
Power Control Center includes an integral self-supporting
base. All equipment is factory leveled.
Purchaser must provide channels and grouting for leveling
all equipment individually.
All bus connections and equipment shipping sections
are coordinated by CP.
Purchaser must coordinate the match up of buses and
shipping spits for different types of equipment.
All equipment is inter-wired and tested before leaving
the CP factory.
Purchaser must coordinate and allow for field labor
to install and interconnect all equipment. This could
include the following: Lighting Transformers
Thermostat Power Panels Exhaust Fan
Lighting Panels Pressurizing Fans Lighting
Fixtures & Receptacles Exterior Lighting
Battery & Charger Air Conditioner
Electric Space Heater. Testing must be done at
site after everything is installed, which adds time
to overall schedule.
Building Inspection
Building permits or labor inspection not required.
Building permits must be obtained at various times during
the project. This causes delays and can add unforeseen
costs.
Insurance Requirements
Power Control Center would be insured at the same rate
as a piece of electrical equipment.
Insurance rates for a building will most likely be more
expensive because of its classification.
Interconnections
All coordinated by CP.
Purchaser must coordinate all interconnecting wiring
and interlocks between different pieces of equipment
within the building.
Receiving, Handling, & Storage
Power Control Centers arrive 14 ft. wide and up to 45
feet long, as a single shipment that can be unloaded
in as little as one hour. Larger buildings will be shipped
in two or more pieces and usually can be unloaded and
set in one day.
Purchaser must provide for receiving several shipments
made at different times for different locations. This
frequently involves: double handling of storage, trucking
from warehouse to location, special protection during
storage, possible pilfering or lost equipment, lost
time due to foul weather, breakage or damage during
storage, drayage, or delays in completing installation
and start-up.
Scheduling
Order can be placed very early since major part of the
engineering, drafting, and coordination is transferred
to the manufacturer.
Procurement is slow and costly. Even a small control
building has all the elements of a major project that
requires expert charts. A series of purchase orders
is required. Requisitions may come from several sources.
Meetings for evaluation, review and coordination are
required. More engineers are required internally. Frequently,
amended specifications and rebidding are introduced.
Experience, planning and a flexible organization enables
CP to make equipment changes throughout the schedule
as the project requirements are evolved.
Coordinating changes is complex. More internal people
are involved. Several outside vendors may be involved.
Formal communications through multiple channels is slow.
Oversights can be expensive.
In general, the total shipping cycle for Power Control
Centers is about the same as indoor equipment of the
same type.
Shipping time will be different for each product type.
The low voltage equipment that ships quickest is most
subject to change because of project changes. This can
result in more time-consuming field changes. Responsibility
for match-up may shift from the vendor to the field.
Schedules and warranties may be affected.
Since the Power Control Center arrives complete and
pre-tested, the field installation time is reduced to
as little as a few days.
Experience has shown that four times the man-hours must
be allotted because of additional work done in the field.
Start-up may be delayed by equipment loss, pilferage,
mismatch or damage in shipment. Last minute modifications
can fall short of the quality built in and tested by
the manufacturer.
Financial
Fixed charges do not begin until after the shipment
of the PCC and payment of invoice, usually 30 days after
the shipment of the unit with all components complete.
Fixed charges begin after receipt and payment of invoices
for individual components and building materials usually
months before building and all components are placed
in service. Additional costs are incurred handling multiple
invoices.
May be depreciated in 8 to 10 years.
Must be depreciated over a 40-year period.
Safety
The
Power Control Center is an offspring of the industry's
old workhorse, the NEMA 3R outdoor, walk-in, and metal
enclosure. It has been widely used and accepted throughout
the industry, i.e. utilities, petroleum, chemical, industrial,
etc. for hazardous and non-hazardous applications. It
offers a better-engineered solution to power distribution
needs, keep critical projects on schedule and yet, is
more economical to purchase.
INDEX
| CORPORATE | PRODUCTS | ENGINEERING | SALES | CONTACT
CIRCUIT BREAKERS | SWITCHGEAR | CUSTOM FABRICATION
TRACTION POWER | FIELD
SERVICE
Copyright © 2000-2005 Controlled Power, LLC.
All Rights Reserved.